9. As a project manager, which of the following situations would concern you the most? a. a three-day delay on an activity with five days

9. As a project manager, which of the following situations would concern you the most?

a. a three-day delay on an activity with five days total float

b. realizing that an activity on your critical path only took two days instead of the four you assigned it using the PERT method

c. a one-day delay to an activity with 0 total float

d. a two-day delay to a noncritical path activity with two predecessor activities

10. How do you calculate Late Start, using the two- pass method?

a. Late Finish-Duration

b. Duration - Early Start

c. Early Finish - Early Start

d. Late Finish - Early Finish

A critical path activity hasing the planning process.

a. the most

b. zero

c. negative float during

d. positive

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Working In Teams Moving From High Potential To High Performance

Authors: Brian A. Griffith ,Ethan B. Dunham

1st Edition

1452286302, 978-1452286303

More Books

Students also viewed these General Management questions