9. Now suppose the activity times for A, B, C, D, E, F, G, H (for the previous example) are as follows: Activity Duration (in

9. Now suppose the activity times for A, B, C, D, E, F, G, H (for the previous example) are as follows:

Activity Duration (in weeks)
A 3
B 4
C 2
D 2
E 4
F 3
G 2
H 1

What is the critical path of the project? How long does the project take to complete?

10. We ask an estimator to verify the duration assessment above (given in Q9). The estimator comes back with a new set of estimates given below, which explicitly factor in uncertainty.

Activity

Best case duration (in weeks)

Most likely case duration

Worst case duration

A

2

3

5

B

2

4

6

C

1

2

3

D

2

2

4

E

3

4

8

F

1

3

6

G

2

2

2

H

1

1

3

a) How long does the project take to complete on average?

b) What is the most likely duration taken to complete the project?

c) Give the histogram for the project duration.

NO 10 USE THIS SIMULATION TOOL : https://sanjiverat.com/pert to answer the relevant questions

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Writing For Hospitality

Authors: Peter Nyhiem, Vivienne J Wildes

1st Edition

0131715712, 9780131715714

More Books

Students also viewed these General Management questions