Question
9. Now suppose the activity times for A, B, C, D, E, F, G, H (for the previous example) are as follows: Activity Duration (in
9. Now suppose the activity times for A, B, C, D, E, F, G, H (for the previous example) are as follows:
Activity | Duration (in weeks) |
A | 3 |
B | 4 |
C | 2 |
D | 2 |
E | 4 |
F | 3 |
G | 2 |
H | 1 |
What is the critical path of the project? How long does the project take to complete?
10. We ask an estimator to verify the duration assessment above (given in Q9). The estimator comes back with a new set of estimates given below, which explicitly factor in uncertainty.
Activity | Best case duration (in weeks) | Most likely case duration | Worst case duration |
A | 2 | 3 | 5 |
B | 2 | 4 | 6 |
C | 1 | 2 | 3 |
D | 2 | 2 | 4 |
E | 3 | 4 | 8 |
F | 1 | 3 | 6 |
G | 2 | 2 | 2 |
H | 1 | 1 | 3 |
a) How long does the project take to complete on average?
b) What is the most likely duration taken to complete the project?
c) Give the histogram for the project duration.
NO 10 USE THIS SIMULATION TOOL : https://sanjiverat.com/pert to answer the relevant questions
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started