Question

1 Approved Answer

9. The amount of time necessary for assembly line workers to complete a product is a normal variable with a mean of 15 minutes

9. The amount of time necessary for assembly line workers to complete a product is a normal variable with a mean of 15 minutes and a standard deviation of 2 minutes. So, 15% of the products require more than minutes for assembly.

Step by Step Solution

3.53 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

Mean Lu 15 standard deviation 6 2 first 15 w... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these Mathematics questions