9. Vision Ware had the following data for the month of July: Actual machine hours 20,000 Total variable overhead (actual) $260,000 Spending Variance $60,000 U
9. Vision Ware had the following data for the month of July:
Actual machine hours | 20,000 |
Total variable overhead (actual) | $260,000 |
Spending Variance | $60,000 U |
Standard machine hours | 100 |
Efficiency Variance | $1,000 F |
What was the standard rate per hour?