Question
1 Approved Answer
9,18 In Exercise 9.16, suppose that the estimates (a, b, m) are given in Table 9.16 and that activity times follow a beta distribution. Use
9,18 In Exercise 9.16, suppose that the estimates (a, b, m) are given in Table 9.16 and that activity times follow a beta distribution. Use the data in the table to calculate the expected activity times, di, and then compute the critical path for each event using dg as the completion time for activity (i, j). Assume that the solution that you obtain is the "planned" time to complete each event, and then find the probabilities that the events will occur without delay 443 TABLE 9.16 Project (a) Activity (a, b, m) Activity (a, b, m) 1,2 (5,8,6) (1,4,3) (2,5, 4) (4,6,5) (7, 10,8) (8, 13,9) (5, 10,9) 3,6 (3,5,4) (4,10,8) (5, 8,6) (9, 15, 10) (4,8,6) (3,5,4) 1,4 4,6 1,5 2,3 2,5 4,7 5,6 5,7 6,7 2,6 3,4 Project (b) Activity Activity (a, b, m) (a, b, m) (12,14, 13) (1,4,3) (5,8,7) (6,9,7) (1,3,2) (3,5,4) (7,9,8) (10,20, 15) 3,7 4,5 4,7 5,6 1,2 (10, 15, 12) (8, 12, 10) (7,11,8) (2,8,4) (5,7,6) 1,3 1,4 1,6 5,7 2,3 6,7 2,5 3,4 Reference: 9.16 Determine the critical path(s) for projects (a) and (b) in the AOA networks in Fig. 9.43. 3 7 8 10 10 4 abao/blo 1ovo 4 3 4 Project (a) 10 3 15 22 10 10 3 12 5 7 6 Project (b) Figure 9.43 Networks for Exercise 9.16. 4
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started