Question
1 Approved Answer
9.19 begin{tabular}{|c|c|c|} hline TASK & PERFORMANCE TIME (min) & TASK MUST FOLLOW TASK LISTED BELOW hline A & 1 & - hline B
9.19
\begin{tabular}{|c|c|c|} \hline TASK & PERFORMANCE TIME (min) & TASK MUST FOLLOW TASK LISTED BELOW \\ \hline A & 1 & - \\ \hline B & 1 & A \\ \hline C & 2 & A \\ \hline D & 1 & C \\ \hline E & 3 & C \\ \hline F & 1 & C \\ \hline G & 1 & D, E, F \\ \hline H & 1 & B \\ \hline I & G, H \\ \hline \end{tabular} 9.19 Because of the expected high demand for Mach 10, Creative Leisure has decided to increase manufacturing time available to produce the Mach 10 (see Problem 9.18). a. If demand remained the same but 300 minutes were available each day on the assembly line, how many workstations would be needed? b. What would be the efficiency of the new system, using the actual number of workstations from (a)? c. What would be the impact on the system if 400 minutes were available? [PX]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started