Question

1 Approved Answer

A 5 pounts each ( 7 . 5 ) A wind energy project of 3 . 0 MW ( WRC$ ) installed capacity requires a

A 5 pounts each (7.5)
A wind energy project of 3.0 MW (WRC$) installed capacity requires a capinal inverment of $2,000.000 The site's capacity finctor is 0.35. Annual operntion ated maintenance costs are 2.0 percent of the iniulal)
NPV=BA[(1+I)n-1I(1+I)n]-{CI[1+m((1+I)n-1I(1+I)n)]}
c=NPV(CA)EI=CI8760n(1PRCF){1+m[(1+I)n-1I(1+1)n]}
n=-ln(1-ICIBA-mCI)ln(1+I)
1)the annual cost of O&M is:
a)20000 USD.
b)30000 USD.
c)40000 USD.
d)50000 USD.
2) the payback period (complex) is approximately:
a) Two years and five months.
b) Throe years and three months.
c) Five years and three months.
d) Seven years and five months.
3) The net present value of the project is approximately in Millions of Dollars
a)1.5 mMs
B)2
c)2.6
d)5.2
4) the lumeth cout Rathet happrowamately
a)1
b)2
c)3
d)4
5)the net prosede value of the herefits in Millichst of Dothans is
a)2.2 Ms
b)3.2 MS
c)4.2 Ms
d)5.2 Ms
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

100 Day Money Saving Challenge

Authors: Clubby Parrot

1st Edition

B0CN9F4XBJ

More Books

Students also viewed these Finance questions

Question

Write an elaborate note on marketing environment.

Answered: 1 week ago