A _ _ _ _ _ _ _ _ _ _ _ _ _ _ monitors work status, machine status, material usage, and availability. Group
A monitors work status, machine status, material usage, and availability.
Group of answer choices
manufacturing execution system
None of these answer choices is correct.
planning and control system
drumbufferrope system