a b) A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if
a b) A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? b. What is the NPV for the project if the required return is 20%? At a required retum of 20% should the firm accept this project? c. At what discount rate would you be indifferent between accepting the project and rejecting it