A B C Activity Predecessor D E F G H conduct a consumer test panel study. Crash Schedule The following data were obtained from

 

A B C Activity Predecessor D E F G H conduct a consumer test panel study. Crash Schedule The following data were obtained from a study of the times required to A B C, D C, D E F Time (Weeks) 4 2 6 2 5 4 5 1 Cost Time (Thousands $) (Weeks) 6 5 4 10 4 7 6 9 6 2 5 6 11 6 5 4 Normal Schedule Cost (Thousands $) 4 3 4 4 6 3 2 2 Crash Rate 2 0.5 0.75 0.5 0.5 1.5 0 1 a) Find the all normal schedule and cost. b) Find the least-cost plan to complete the project in 21 days. (Assume minimum partial crashing of 1 week)

Step by Step Solution

3.51 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

ANSWER a To find the normal schedule and cost we do not need the crash schedule and crash rate We can simply use the normal schedule and the cost given in the table Activity Predecessor Normal Schedul... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these Marketing questions

Question

What would you suggest to recover the project?

Answered: 1 week ago