Question
A B C D E F G H I J Most Optimistic 3 5 5 3 10 2 5 10 10 18 Most Likely 15
A | B | C | D | E | F | G | H | I | J | |
Most Optimistic | 3 | 5 | 5 | 3 | 10 | 2 | 5 | 10 | 10 | 18 |
Most Likely | 15 | 8 | 8 | 10 | 15 | 5 | 9 | 15 | 12 | 20 |
Worst Case Time | 36 | 24 | 12 | 15 | 22 | 8 | 25 | 33 | 32 | 30 |
PERT-MEAN | 16.50 | 10.17 | 8.17 | 9.67 | 15.33 | 5.00 | 11.00 | 17.17 | 15.00 | 21.33 |
SD | 5.50 | 3.17 | 1.17 | 2.00 | 2.00 | 1.00 | 3.33 | 3.83 | 3.67 | 2.00 |
Variance | 30.25 | 10.03 | 1.36 | 4.00 | 4.00 | 1.00 | 11.11 | 14.69 | 13.44 | 4.00 |
Please answer the following with the formulas/work.
Question 1. Assume that activity A took 20 days to complete. Upon completion of activity A, the project planner wants to determine the probability that project will be completed in 80 day? What is the probability?
Question 2. Assume that activity A took 20 days to complete. Activity times for B, D and F remained unchanged but activity C took 10.2 days to complete. What is the probability that project will be completed in 80 days based on project progress at the end of 30.2 days?
Question 3. Assume that activity A took 16.5 days, B 12 days, F 8 days, and E 10 days. Activity times for C and D remained unchanged. What is the probability that project will be completed in 80 days based on the project progress at the end of 3.5 days?
Question 4. Assume that activities A and B took 16.5 and 10.2 days, respectively. If activity E takes 17 days and H takes 20 days, what is the probability that project will be completed in 80 days upon completion of activity H? What should be the new activity time for activity J to have probability of completion to be .95?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started