a - b ) Using Johnson's rule for 2 - machine scheduling, the sequence is: Job;Printing ( hours ) ;Binding ( hours ) T; 1

a-b) Using Johnson's rule for2-machine scheduling, the sequence is: Job;Printing (hours);Binding (hours)
T;10;8
U;3;4
V;6;2
W;12;7
X;5;1
Y;14;13
Z;9;11
Scheduled Order
Job
1
U
Part 2
2
Z
Part 3
3
Y
Part 4
4
T
Part 5
5
W
Part 6
6
V
Part 7
7
X
Part 8
c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs(including binding)= enter your response here hours (enter your response as a whole number). D) the idle time in binding shop based on the sequence developed using Johnson's rule : amount of hours?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The General Model Of Working Capital Management

Authors: Rodrigo Zeidan

1st Edition

9811933332, 978-9811933332

More Books

Students also viewed these General Management questions

Question

Describe global employee and labor relations practices.

Answered: 1 week ago