A builder has produced a quote for some alterations. The price is made up as follows: $ Direct materials (100 kg @ $4 per kg)
A builder has produced a quote for some alterations. The price is made up as follows:
$
Direct materials
(100 kg @ $4 per kg)
400
Direct labour
(5 hours @ $10 per hour)
50
(15 hours @ $5 per hour)
75
Hire machine
(1 day @ $100 per hour)
100
Overheads
(20 hours @ $8 per hour)
160
Total costs
785
Profit@ 20% of cost 0.2 x $785
157
Price quoted
$942
Actual costs for the job were as follows:
Direct materials
(120 kg @ $4 per kg)
Direct labour
(3 hours @ $10 per hour)
(20 hours @ $5 per hour)
Hire a machine
(2 days @ $100 per hour)
The actual profit/(loss) made in thejob was:
A.$52 loss
B.$28 loss
C.$28profit
D.$52 profit
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started