A cell uses 9 6 kg of a certain material each day. The material is transported in vats that hold 5 8 kg each. Cycle

A cell uses 96 kg of a certain material each day. The material is transported in vats that hold 58 kg each. Cycle time for a kanban is about four hours. The manager has assigned a safety factor of 1.00. The plant operates on an eight-hour day.
How many kanbans are needed? (Round the final answer to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: James P. Lewis

3rd Edition

0814408796, 978-0814408797

More Books

Students also viewed these General Management questions

Question

Contrast intelligence and emotional intelligence.

Answered: 1 week ago

Question

Briefly describe four guides to ethical decision-making

Answered: 1 week ago