A certain company is planning to run a project whose activities are summarized in the table below. table [ [ , , , ]

A certain company is planning to run a project whose activities are summarized in the table below.
\table[[,,,],[Task ID,Description,\table[[Immediate],[Predecessor]],\table[[Duration],[(months)]]],[1,Install New Software Package,,],[2,Assess Requirements,,],[3,Assess Requirements,--,1.0],[4,Design,,],[5,Design Business System,3,2.5],[6,Develop,,2.0],[7,Modify Purchased Package,5,1.5],[8,Modify-In-House Procedures,5,4.0],[9,Modify Manual Systems Flow,,1.5],[10,Test,7,1.0],[11,Test Purchased Package,8,1.0],[12,Test In-House Procedures,9,1.5],[13,Test Manual Systems Flow,,0.5],[14,Implement,11,12,13,],[15,Implement New Software Package,11,12,13,],[16,Train Staff,,]]
a) How many months will it take to complete the project?
b) Which activities are critical?
c) What is the total slack for each of the activities that are not critical?
d) If the project were started on June 3,2024, and observed all the US Legal holidays, on what day will the project be completed?A certain company is planning to run a project whose activities are summarized in the table below.
Task ID
Description
Immediate Predecessor
Duration (months)
1
Install New Software Package
2
Assess Requirements
3
Assess Requirements
--
1.0
4
Design
5
Design Business System
3
2.5
6
Develop
7
Modify Purchased Package
5
2.0
8
Modify-In-House Procedures
5
1.5
9
Modify Manual Systems Flow
5
4.0
10
Test
11
Test Purchased Package
7
1.5
12
Test In-House Procedures
8
1.0
13
Test Manual Systems Flow
9
1.0
14
Implement
15
Implement New Software Package
11,12,13
1.5
16
Train Staff
11,12,13
0.5
a) How many months will it take to complete the project?
b) Which activities are critical?
c) What is the total slack for each of the activities that are not critical?
d) If the project were started on June 3,2024, and observed all the US Legal holidays, on what day will the project be completed?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions