A certain project activity has a total slack of 0 days mean it is one the project's critical path. If this activity gets delayed by
A certain project activity has a total slack of 0 days mean it is one the project's critical path. If this activity gets delayed by 1 day, the project finish date will get delayed by
A. 0 days
B. 1 day
C. 2 days
D. 3 days