Question

1 Approved Answer

A certain project activity has a total slack of 0 days mean it is one the project's critical path. If this activity gets delayed by

A certain project activity has a total slack of 0 days mean it is one the project's critical path. If this activity gets delayed by 1 day, the project finish date will get delayed by

A. 0 days

B. 1 day

C. 2 days

D. 3 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management In The Sport Industry

Authors: Matthew T. Brown, Daniel A. Rascher, Mark S. Nagel, Chad D. McEvoy

3rd Edition

0367321211, 978-0367321215

More Books

Students also viewed these Finance questions