A company has estimated net requirements for a particular part as follows: Month 1 2 3 4 5 6 7 8 9 10 11 12
A company has estimated net requirements for a particular part as follows:
| Month |
|
|
|
| |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Requirements | 100 | 10 | 15 | 20 | 70 | 250 | 250 | 250 | 250 | 40 | 0 | 100 |
Ordering cost associated with this part is $300. Estimated inventory carrying cost is $2 per unit per month calculated on average inventory. Currently no parts are available in inventory. The company wishes to know when and how much to order over the next 12 months.
(a) Apply the economic order quantity and the part period balancing procedures to solve this problem.
(b) What important assumptions are involved in each of the approaches used in part a?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started