A company has recently implemented a standard cost system.The company's cost accountant has provided the following data toperform a variance analysis for May: Standard Cost
A company has recently implemented a standard cost system.The company's cost accountant has provided the following data toperform a variance analysis for May:
Standard Cost Information: direct material standardprice $12 per pound
standard quantity allowed perunit 4 pounds per unit
direct labor standardrate $7per hour
standard hours allowed perunit 0.5 hours per unit
fixed overheadbudgeted $24,000 per month
normal level ofproduction 12,000 units per month
variable overhead applicationrate $1.80 per unit
fixed overhead application rate
( $24,000/12,000units) $2.00per unit
total overhead applicationrate $3.80 per unit
Actual Cost Information: cost of material purchased &used $429,000
pounds of materials purchased &used 39,000 pounds
cost of directlabor $23,100
hours of directlabor 4,200 hours
cost of variableoverhead $17,750
cost of fixedoverhead $24,200
actual volume ofproduction 10,000 units
Compute the following variances, Indicate whether eachvariance if favorable or unfavorable
d. labor efficiency variance:$__________
e. overhead spending variance:$________
f. overhead volume variance:$________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started