A company in Sussex has developed a small motorised craft, the Deluxe. Construction of the Deluxe in the companys backyard is a two man operation.

A company in Sussex has developed a small motorised craft, the Deluxe. Construction of the Deluxe in the companys backyard is a two man operation. Harry is paid 12.75 an hour and Edward is paid 9.60 an hour.

The time taken by the two employees to make the first boat in May was as follows:

Harry

Skilled employee

220 hours

Edward

Semi-skilled employee

410 hours

Experience has shown that where the construction of a motorised craft is concerned, the use of skilled labour is associated with an 85% learning effect and the semi-skilled labour is associated with a 90% learning effect.

During the month of July the fourth and fifth boats were assembled from start to finish.

You are required to:

  1. Calculate the total budgeted time for the boats assembled in July, and total labour cost for the boats assembled in July.
  2. Discuss the possible problems that could be associated with ignoring the learning curve when estimating costs.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Making Use Of Clinical Audit A Guide To Practice In The Health Professions

Authors: Sally J. Redfern, Anemone Kober, Maurice Kogan

1st Edition

0335195423, 978-0335195428

More Books

Students also viewed these Accounting questions

Question

Which four factors influence the strength of personal norms?

Answered: 1 week ago

Question

How can the Internet be helpful in a job search? (Objective 2)

Answered: 1 week ago