A company is designing a product layout for a new product. It plans to use this production line seven hours a day in order
A company is designing a product layout for a new product. It plans to use this production line seven hours a day in order to meet projected demand of 252 units per day. The tasks necessary to produce this product are detailed in the table below. Time Task Predecessor (seconds) A 60 B A 36 C E 26 DE 23 B, D 65 F E 30 What is the percentage of idle time? %