Question
1 Approved Answer
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
Task | Time(secs) | Immediate Predecessor |
u | 30 | none |
v | 30 | u |
w | 6 | u |
x | 12 | w |
y | 54 | x |
z | 30 | v,y |
Without regard to demand, what is the minimum possible cycle time (in seconds) for this situation?
Incorrect answer:
162
72
, Not Selected
54
, Not Selected
30
, Not Selected
6
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started