A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:

Task

Time(secs)

Immediate Predecessor

u

30

none

v

30

u

w

6

u

x

12

w

y

54

x

z

30

v,y

Without regard to demand, what is the minimum possible cycle time (in seconds) for this situation?

Incorrect answer:

162

72

, Not Selected

54

, Not Selected

30

, Not Selected

6

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions