A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
Task Time(secs) Immediate
Predecessor
u 30 none
v 30 u
w 6 u
x 12 w
y 54 x
z 30 v,y
If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the theoretical minimum number of workstations?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing and Assurance Services A Systematic Approach

Authors: William Messier, Steven Glover, Douglas Prawitt

9th edition

1308361491, 77862333, 978-1259248290, 9780077862336, 1259162346, 978-1259162343

Students also viewed these General Management questions