Question
A company is producing a part that requires processing on three different machines. The machining sequence requires that the part move from machine 1to machine
A company is producing a part that requires processing on three different machines. The machining sequence requires that the part move from machine 1to machine 2 and then to machine 3. The annual demand is estimated at 600,000 units of that part. The company works 250 days per year and 8 hours per day. The reliability of each machine is taken at 90%. The batch size is equal to the daily production volume. The relevant data is shown below:
| Machine | ||
1 | 2 | 3 | |
Processing cycle time (seconds/part) | 8 | 12 | 10 |
Loading + unloading time (seconds/part) | 3 | 4 | 3 |
Average Setup time (in minutes)/batch | 20 | 20 | 30 |
Defects (%) | 5 | 6 | 4 |
Efficiency ( %) | 90 | 88 | 95 |
Average down time (in minutes)/day | 15 | 10 | 15 |
Please answer the following questions (Show your calculations)
- Determine the number of units that must be produced each day by each machine if all defective units are scrapped.
- Determine the number of machine 2 needed
- Determine the minimum number of operators needed for machine 3
- Determine the average utilization for machine 1
- Determine the average operator idle time for machine 3
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started