A company makes motor assemblies in lot sizes of 35 units, for which there is a lead time of 2 weeks. The motors are are
- A company makes motor assemblies in lot sizes of 35 units, for which there is a lead time of 2 weeks. The motors are are made up of spindles ( 2 spindles per motor) which are made in lots of 50 units, and lead time of 1 week. They have 25 spindles on hand. The following is the demand for the motors:
Complete the MRP charts for Motor and Spindle Requirements
Week | 4 | 5 | 6 | 7 | 8 |
Demand | 5 | 10 | 10 | 10 | 30 |
MRP Chart for the MOTOR Lead time : 2 weeks Lot size 35 units
Period (Week No.) | Past | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross Requirements | |||||||||
Scheduled Receipts | |||||||||
On Hand | |||||||||
Net Requirements | |||||||||
Planned Order Release |
MRP Chart for the SPINDLE Lead time: 1 week Lot size 50units
Period (Week No.) | Past | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross Requirements | |||||||||
Scheduled Receipts | |||||||||
On Hand | |||||||||
Net Requirements | |||||||||
Planned Order Release |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started