A Company manufactures two products: Product B and Product C. The company uses a plant-wide overhead rate based on direct labor-hours. Total estimated overhead cost
A Company manufactures two products: Product B and Product C. The company uses a plant-wide overhead rate based on direct labor-hours. Total estimated overhead cost is $833,000. Direct labor hours for the two products are: Product B Product C 6,000 DLH 4,000 DLH Using the plant-wide overhead rate, how much manufacturing overhead cost would be allocated to Product C? O $208.25 $333,200. O $555,333. $499,800