A company needs to produce 600 units per day, currently the company works 2 shifts of 4 hours a day each and with 2 breaks
A company needs to produce 600 units per day, currently the company works 2 shifts of 4 hours a day each and with 2 breaks of 15 minutes each shift. The product is manufactured on an assembly line. What is the cycle time that the production line should have? Possible anwers are a) 0.75 minutes b) 45 seconds c) 0.7 minutes d) 7 minutes