A company operates 8 hours per shift, two shifts per day, five days a week with 10 hours maintenance per week and other downtime of
A company operates 8 hours per shift, two shifts per day, five days a week with 10 hours maintenance per week and other downtime of 2 hours per week.
What is the effective capacity in hours per week?