A company operates a job costing system. Job number 1012 requires $45 of direct materials and $30 of direct labor. Direct labor is paid at
A company operates a job costing system. Job number 1012 requires $45 of direct materials and $30 of direct labor. Direct labor is paid at the rate $7.50 per hour. Production overheads are applied at a rate of $12.50 per direct labor hour and other overheads are applied at a rate of 60% of prime cost. What is the total cost for job number 1012? $170.00 O $200.00 $240.00 $195.00