Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A company produces an end item E . One unit of item E can be made by assembling 1 unit of A , 1 unit

A company produces an end item E. One unit of item E can be made by assembling 1 unit of A,1
unit of B, and 2 units of C. One unit of A is made of 1 unit of C and 2 units of D; one unit of B is
assembled by using 2 units of M and 1 unit of N. On-hand inventories are 50 units of A and 45 units
of C. Scheduled receipts are 50 units of A at the beginning of Week 1,100 units of C at the beginning
of Week 1, and 100 units of C at the beginning of Week 2.
Lead times for subassemblies A and B are 1 week, and lead times for other components are 2
weeks. Final assembly of E requires 1 week.
1. Fill in Table 1 to prepare a master production schedule for end item E using the fixed-periodof-two policy. The beginning inventory for E is 108 units; the forecast and promised customer
orders for end item E are provided in this table. [4 marks]
Week 12345678
Forecast 4545506060505045
Customer orders (committed)42385135201510
Projected on-hand inventory
Net Inventory before MPS
MPS Receipt
MPS Start
Available-to-promise inventory (uncommitted)
Table 1: MPS table for end item E in Question 1
2. Construct a product structure tree (i.e., a BOM chart).[4 marks]
Answer:
1
BUS 2211: Operations Management Assignment 4
3. Use your master production schedule (i.e., MPS Start) in Table 1 to develop a material requirement plan (MRP) for subassembly A using the lot-for-lot policy. [4 marks]
Week 12345678
MPS Start for E
A
Lead Time: 1 week; On Hand: 50 units; Lot Size: lot-for-lot;
Scheduled Receipts: 50 units in Week 1
Gross Requirement
Scheduled Receipts
Projected On Hand
Net Requirements
PO Receipts
PO Releases
4. Use your master production schedule in Table 1 and your MRP schedule for subassembly A to
develop a material requirement plan (MRP) for component C using the lot size of 100 units
ordering policy. [4 marks]
Week 12345678
C
Lead Time: 2 weeks; On Hand: 45 units; Lot Size: 100 units;
Scheduled Receipts: 100 units in Week 1 and 100 units in Week 2
Gross Requirement
Scheduled Receipts
Projected On Hand
Net Requirements
PO Receipts
PO Releases
5. You are required to calculate the total inventory cost for component C during the
eight weeks. Note that, for each week, the inventory cost includes a fixed cost and a holding
cost. We assume that the per order fixed cost is $200/order, and the unit holding cost is $1
per item per week. The fixed cost is incurred each time when the firm places an order. More
precisely, if the firm places an order at the beginning of a week, then the firm incurs the fixed
cost for this week; otherwise, the fixed cost for the week is zero. The holding cost is calculated
according to the number of remaining items at the end of each week. For example, if 10 units
of component C are remaining at the end of a week, then the holding cost for this week is
10\times $1= $10.[4 marks]
Answer:
2
BUS 2211: Operations Management Assignment 4
6. Use your master production schedule in Table 1 and your MRP schedule for subassembly A to
develop a material requirement plan (MRP) for component C using fixed-period-of-two policy.
[4 marks]
Week 12345678
C
Lead Time: 2 weeks; On Hand: 45 units;
Lot Size: fixed-period-of-2;
Scheduled Receipts: 100 units in Week 1,100 units in Week 2
Gross Requirement
Scheduled Receipts
Projected On Hand
Net Requirements
PO Receipts
PO Releases
7. Calculate the total inventory cost for the fixed-period-of-two policy in Question 6. The per order
fixed cost is still $200/order, and the unit holding cost is still $1 per item per week.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Operations Research

Authors: Frederick Hillier, Gerald Lieberman

8th Edition

0073211141, 9780073211145

More Books

Students also viewed these General Management questions