Question
A company produces an end item E. One unit of item E can be made by assembling 1 unit of A, 1 unit of B,
A company produces an end item E.
One unit of item E can be made by assembling 1 unit of A, 1 unit of B, and 2 units of C.
One unit of A is made of 1 unit of C and 2 units of D;
One unit of B is assembled by using 2 units of M and 1 unit of N.
On-hand inventories are 50 units of A and 45 units of C.
Scheduled receipts are 50 units of A at the beginning of Week 1, 100 units of C at the beginning of Week 1, and 100 units of C at the beginning of Week 2.
Lead times for subassemblies A and B are 1 week, and lead times for other components are 2 weeks.
Final assembly of E requires 1 week. 1.
- Fill in Table 1 to prepare a master production schedule for end item E using the fixed-period-of-two policy. The beginning inventory for E is 108 units; the forecast and promised customer orders for end item E are provided in this table.
Week 1 2 3 4 5 6 7 8
Forecast 45 45 50 60 60 50 50 45
Customer orders (committed) 42 38 51 35 20 15 10
Projected on-hand inventory ?
Net Inventory before MPS ?
MPS Receipt ?
MPS Start Available-to-promise inventory (uncommitted)?
2. Construct a product structure tree (i.e., a BOM chart)?
3. Use your master production schedule (i.e., MPS Start) in Table 1 to develop a material requirement plan (MRP) for subassembly A using the lot-for-lot policy.
Week 1 2 3 4 5 6 7 8
MPS Start for E
A - Lead Time: 1 week; On Hand: 50 units; Lot Size: lot-for-lot; Scheduled Receipts: 50 units in Week 1
Gross Requirement ?
Scheduled Receipts?
Projected On Hand ?
Net Requirements ?
PO Receipts?
PO Releases ?
4. Use your master production schedule in Table 1 and your MRP schedule for subassembly A to develop a material requirement plan (MRP) for component C using the lot size of 100 units ordering policy. [
Week 1 2 3 4 5 6 7 8
C - Lead Time: 2 weeks; On Hand: 45 units; Lot Size: 100 units; Scheduled Receipts: 100 units in Week 1 and 100 units in Week 2
Gross Requirement ?
Scheduled Receipts ?
Projected On Hand ?
Net Requirements ?
PO Receipts ?
PO Releases?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started