A company provided the following direct materials cost information. Compute the total direct materials cost variance. Standard costs assigned: Direct materials standard cost (429,000 units
A company provided the following direct materials cost information. Compute the total direct materials cost variance. Standard costs assigned: Direct materials standard cost (429,000 units @ $2.00 / unit) Actual costs: Direct materials costs incurred (427,750 units @ $2.20 / unit) $858,000 $941, 850 Multiple Choice $83.050 Favorable. $85.550 Favorable. $85,550 Unfavorable $83.050 Unfavorable $2.500 Favorable