Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A company requires federal funding for a park-and-ride project. Federal funding application requires the project plan for the design phase. You are tasked to
A company requires federal funding for a park-and-ride project. Federal funding application requires the project plan for the design phase. You are tasked to prepare a project plan based on the information collected from various stakeholders involved in the project. Consider that the project starts at day 0 and must be completed in 155 days from the start date. Use the information provided in Table 1 to answer the question 1, 2 and 3. + Table 1 Activity # Activity Name ED IP 1 Conduct Survey 5 - 2 Complete Soil Reports 20 1 3 Design Traffic System 30 1 4 Develop Lot Layout 5 1 5 Approve Design 80 2,3,4 6 Develop Illumination Plan 15 7 Develop Drainage Plan 30 8 Develop Landscape Plan 25 9 10 Complete Signage Designs Integrate and Validate Designs 15 10 50 50 50 559 6,7,8, ED = estimated duration IP = immediate predecessor 1. Develop network diagram and clearly label ES, EF, LS, LF, TS, and critical path. *Develop the network diagram in Excel and paste the network diagram here as an image 2. Which activities are on the critical path? 3. Suggest two recommendations to bring the project back on track. Justify your choice of recommendations. 4. Use information provided on the actual finish (AF) in Table 2 to calculate the following. *use an actual finish to update ES, EF, LS, LE, TS, and Critical path Table 2 Activity # Activity Name ED IP AF 1 Conduct Survey 5 6 2 Complete Soil Reports 20 1 28 3 Design Traffic System 30 1 35 4 Develop Lot Layout 5 1 5 Approve Design 75 2,3,4 6 Develop Illumination Plan 15 5 7 Develop Drainage Plan 30 5 8 Develop Landscape Plan 25 5 9 Complete Signage Designs 15 5 10 Designs Integrate and Validate *Develop the network diagram in Excel and paste the network diagram here as an image 10 6,7,8, 9 A company requires federal funding for a park-and-ride project. Federal funding application requires the project plan for the design phase. You are tasked to prepare a project plan based on the information collected from various stakeholders involved in the project. Consider that the project starts at day 0 and must be completed in 155 days from the start date. Use the information provided in Table 1 to answer the question 1, 2 and 3. + Table 1 Activity # Activity Name ED IP 1 Conduct Survey 5 - 2 Complete Soil Reports 20 1 3 Design Traffic System 30 1 4 Develop Lot Layout 5 1 5 Approve Design 80 2,3,4 6 Develop Illumination Plan 15 7 Develop Drainage Plan 30 8 Develop Landscape Plan 25 9 10 Complete Signage Designs Integrate and Validate Designs 15 10 50 50 50 559 6,7,8, ED = estimated duration IP = immediate predecessor 1. Develop network diagram and clearly label ES, EF, LS, LF, TS, and critical path. *Develop the network diagram in Excel and paste the network diagram here as an image 2. Which activities are on the critical path? 3. Suggest two recommendations to bring the project back on track. Justify your choice of recommendations. 4. Use information provided on the actual finish (AF) in Table 2 to calculate the following. *use an actual finish to update ES, EF, LS, LE, TS, and Critical path Table 2 Activity # Activity Name ED IP AF 1 Conduct Survey 5 6 2 Complete Soil Reports 20 1 28 3 Design Traffic System 30 1 35 4 Develop Lot Layout 5 1 5 Approve Design 75 2,3,4 6 Develop Illumination Plan 15 5 7 Develop Drainage Plan 30 5 8 Develop Landscape Plan 25 5 9 Complete Signage Designs 15 5 10 Designs Integrate and Validate *Develop the network diagram in Excel and paste the network diagram here as an image 10 6,7,8, 9
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Developing the network diagram To create a network diagram we need to identify the immediate predecessors and calculate the Early Start ES Early Finish EF Late Start LS Late Finish LF Total Slack TS a...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started