A company was contracted to build a tunnel on 1st Jan 2011 and prepared accounts on 31st December each year. Total contract revenue 200,000 Total

A company was contracted to build a tunnel on 1st Jan 2011 and prepared accounts on 31st

December each year.

Total contract revenue 200,000

Total contract costs 80,000

Actual contract costs incurred (Year 1) 50,000

Progress billings 60,000

Costs actually incurred 31,000

Showing full working, calculate the contract account (asset/liability) balance for the year.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Risk Assessment Made Easy Seeing What Others Miss

Authors: Charles Hall

1st Edition

0578961679, 978-0578961675

More Books

Students also viewed these Accounting questions