A company was planning to build a bridge with an initial budgeted cost of 5000000. After value management, the budgeted cost of the bridge was
A company was planning to build a bridge with an initial budgeted cost of 5000000. After value management, the budgeted cost of the bridge was down by 15%. The value for money for the bridge after the value management process also improved by 5 %. Calculate the project value improvement after the value management process. Please give your answer as a percentage correct to 2 decimal places