A company who produces two different products, Product X and Product Y, Is busy to evaluate the activity-based environmental cost of each product The following
A company who produces two different products, Product X and Product Y, Is busy to evaluate the activity-based environmental cost of each product
The following Is Information on two of the environmental activities
Activity |
Driver | Cost R |
Maintenance of pollution equipment | Maintenance hours | 120,000 |
Disposal of toxic waste | Kilograms of waste | 80,000 |
The following data Is available for Product X and Product Y
| Product X | Product Y |
Non-environmental production costs | R400,000 | R500,000 |
Number of units produced | 100,000 | 200,000 |
Maintenance hours for pollution equipment | 1,000 | 4,000 |
Toxic waste In Kilograms | 10,000 | 30,000 |
3 1 Assign the environmental activity costs to Product X and to Product Y (2)
- Calculate the unit environmental cost of Product X (2)
- Calculate the unit environmental cost of Product Y (2)
- Calculate the overall unit cost of Product X (2)
- Calculate the overall unit cost of Product Y (2)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started