Question
A company's production facility, consisting of two identical machines, currently caters only to product A. The annual demand for the product is 4000 units. Management
A company's production facility, consisting of two identical machines, currently caters only to product A. The annual demand for the product is 4000 units. Management has now decided to introduce another product, B, which uses the same facilities as that of product A. Product B has an annual demand of 2000 units. In view of the uncertainties involved in producing two products, management desires to have an overall 10 percent capacity cushion. Given the following additional information about processing requirements, how many more machines are required? (Assume 8 hours/shift, 2 shifts/day, 250 days/year, and that no overtime is allowed).
Product | Processing Time per Unit (in hours) | Setup time per Batch (in hours) | Batch (Lot) Size (units) |
A | 2.0 | 8 | 100 |
B | 2.8 | 16 | 200 |
Show your calculations for each question at the bottom of the question. Without the solution, an incorrect answer will receive 0 points and correct answers may not receive full points. The shown work will help me see where the error is and provide appropriate partial credit and feedback.
Using the information above, what is the total number of hours required of the machines to meet the annual demand for product A?
Using the information above, what is the total number of hours required of the milling machine to meet the annual demand for product B?
What is the company's current annual capacity per machine?
How many additional machines are required?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Total Hours Required for Product A To calculate the total number of hours required for product A we ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3