A. Compute the NPV of the following cash flow schedule using the time value of money/mathematical formula DO NOT use any TVM-related Excel functions to
A. Compute the NPV of the following cash flow schedule using the time value of money/mathematical formula | |||||||
DO NOT use any TVM-related Excel functions to produce your answer | |||||||
B. Is this a value-enhancing project? | |||||||
The discount rate is | 11.9% | ||||||
Time | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
CFs | -200 | -100 | 0 | 120 | 120 | 120 | 100 |
SHOW WORK HERE, HIGHLIGHT FINAL ANSWER IN YELLOW |