A concrete structure consists of 14 columns to support an elevated floor slab. The columns are 18 inches square and 10 feet high. Assume there

A concrete structure consists of 14 columns to support an elevated floor slab. The columns are 18 inches square and 10 feet high. Assume there will be no reuse of column forms. Estimate the total cost and cost per SFCA for building, erecting and removing the formwork for these columns. Refer tables to find out quantities of materials and labor hours required for these columns. Use average values in the table for estimating purpose.

Plywood of 4 x 8 ft will be used. The application rate of form oil is 400 SFCA per gallon. All the columns will be erected simultaneously. The clamps will be rented.

The following cost information applies: (15 points)

  • Plywood sheet (4 x 8 ft): $35.00 per sheet
  • Lumber: $0.70 per bf
  • Clamp: $4.00 per clamp for renting
  • Form Oil: $8.50 per gallon
  • Carpenters: $25.00 per hour
  • Laborer: $17.00 per hour

Step by Step Solution

3.42 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

Total no of columns 14 Height of one column 10 ft Total surface area of board required fo... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Algebra and Trigonometry

Authors: Ron Larson

10th edition

9781337514255, 1337271179, 133751425X, 978-1337271172

More Books

Students also viewed these Accounting questions

Question

Explain the term suboptimization.

Answered: 1 week ago