( a ) . Consider the following configuration of machines, which represent an unbalanced line with multi - machine stations. Station Number 1 2 3

(a). Consider the following configuration of machines, which represent an unbalanced line with multi-machine stations.
Station
Number
1
2
3
Total
Number of
Machines
3
6
4
13
Process
Time
3 mts
8 mts
5 mts
16 mts
There is a proposal to replace these 13 machines by a modern super fast computer controlled machine which will perform all the operations of station numbers 1 to 3, with a processing time of 7 mts per job. This new machine requires only two skilled operators and there is expected to be considerable savings in electricity cost / unit of production too.
Evaluate the proposal.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to Management Science Quantitative Approach to Decision Making

Authors: David R. Anderson, Dennis J. Sweeney, Thomas A. Williams, Jeffrey D. Camm, James J. Cochran

15th edition

978-1337406529

More Books

Students also viewed these General Management questions