A construction company is planning to build separate hotel How many years the hotels can finish and how many workers are required each year are given in the table below. When the hotel are finished their annual earnings will be as follows: 1st hotel: 50,000, 2nd hotel: 10,000 and 3rd hotel 40,000. The company has to decide which projects will be realized and even if it will be readed, in which year the construction will start. The following points should be considered when deciding which hotel will be built in which year. 1) A maximum of 50 workers can be used each year 2) At most one hotel construction can be started each year, 3) Hotel 2 must be completed at the end of the 4th year, HOTEL CONSTRUCTION TIMELYEAR) NUVISER OF REQUIRED WORKERS PER YEAR 1 2 3 2 2 3 20 20 Establish a 0.1 integer model that will maximire the total canings of AEK construction at the end of years. Define the model on excel and find the result A construction company is planning to build 3 separate hotels. How many years the hotels can finish and how many workers are required each year are given in the table below. When the hotels are finished, their annual earnings will be as follows: 1st hotel: 50,000, 2nd hotel: 30,000 and 3rd hotel: 40,000. The company has to decide which projects will be realized and even if it will be realized, in which year the construction will start. The following points should be considered when deciding which hotel will be built in which year. 1) A maximum of 60 workers can be used each year, 2) At most one hotel construction can be started each year. 3) Hotel 2 must be completed at the end of the 4th year HOTEL CONSTRUCTION TIME(YEAR) 1 NUMBER OF REQUIRED WORKERS PER YEAR 30 20 20 2 2 3 2 3 Establish a 0-1 integer model that will maximize the total earnings of AEK construction at the end of 5 years. Detine the model on excel and find the result. A construction company is planning to build separate hotel How many years the hotels can finish and how many workers are required each year are given in the table below. When the hotel are finished their annual earnings will be as follows: 1st hotel: 50,000, 2nd hotel: 10,000 and 3rd hotel 40,000. The company has to decide which projects will be realized and even if it will be readed, in which year the construction will start. The following points should be considered when deciding which hotel will be built in which year. 1) A maximum of 50 workers can be used each year 2) At most one hotel construction can be started each year, 3) Hotel 2 must be completed at the end of the 4th year, HOTEL CONSTRUCTION TIMELYEAR) NUVISER OF REQUIRED WORKERS PER YEAR 1 2 3 2 2 3 20 20 Establish a 0.1 integer model that will maximire the total canings of AEK construction at the end of years. Define the model on excel and find the result A construction company is planning to build 3 separate hotels. How many years the hotels can finish and how many workers are required each year are given in the table below. When the hotels are finished, their annual earnings will be as follows: 1st hotel: 50,000, 2nd hotel: 30,000 and 3rd hotel: 40,000. The company has to decide which projects will be realized and even if it will be realized, in which year the construction will start. The following points should be considered when deciding which hotel will be built in which year. 1) A maximum of 60 workers can be used each year, 2) At most one hotel construction can be started each year. 3) Hotel 2 must be completed at the end of the 4th year HOTEL CONSTRUCTION TIME(YEAR) 1 NUMBER OF REQUIRED WORKERS PER YEAR 30 20 20 2 2 3 2 3 Establish a 0-1 integer model that will maximize the total earnings of AEK construction at the end of 5 years. Detine the model on excel and find the result