A construction project at day 70 has actual costs of $78,000 and a scheduled cost of $84,000. The Work Package Manager estimates a value completed
A construction project at day 70 has actual costs of $78,000 and a scheduled cost of $84,000. The Work Package Manager estimates a value completed of $81,000. Calculate SV & CV, CPI, and SPI. What does this tell you?