A construction project consists of the following activities: Activity | Predecessor | Duration (weeks) A | - | 2 B | - | 4 C
A construction project consists of the following activities:
Activity | Predecessor | Duration (weeks)
A | - | 2
B | - | 4
C | A | 3
D | B | 6
E | B | 5
F | C, D | 4
G | E, F | 7
What is the critical path of the project, and how long will it take to complete?