A contractor enters into a revenue contract with a customer to build customized equipment for $80,000 with a performance bonus of $44,000 that will be

A contractor enters into a revenue contract with a customer to build customized equipment for $80,000 with a performance bonus of $44,000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar contracts and thus has the data to predict the timing of completion of the contract. Therefore, the contractor concludes that the expected value method is the best predictor of revenue. The contractor estimates that there is a 65% probability that the contract will be completed by the agreed-upon completion date, a 25% probability that it will be completed one week late, and a 10% probability that it will be completed two weeks late.

Complete the following table in order to determine the transaction price for revenue recognition for the contractor. Round each amount in the table to the nearest dollar.

Consideration Bonus Amount Probability of Outcome Revenue Recognized
Bonus if completed on agreed-upon date Answer Answer Answer
Bonus if completed one week late Answer Answer Answer
Bonus if completed two weeks late Answer Answer Answer
Variable consideration Answer
Fixed consideration Answer
Total transaction price Answer

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions