A contractor has to move 15 300 Bank m 3 of wet sandy material in rear dump trucks, which will be loaded by an excavator.

A contractor has to move 15 300 Bank m3of wet sandy material in rear dump trucks, which will be loaded by an excavator. Average face depth will be 2.4 m with 60-90 degree average swing angle. Ten days are available to do the work. The Contractor plans to work 10 hours/day and estimates a 50 min. work hour (83% job efficiency). There are two excavators that could be made available to do the work: Excavator A (320) with 1.0 m3bucket or Excavator B (336) with 1.9 m3bucket.

If the swell factor is 25%, calculate the total volume of loose material to be moved.

Calculate the required productivity.

Propose a fill factor and justify it.

Estimate the actual bucket payloads (actual amount of material in the bucket).

Could this job be done with either machine or will the excavator B have to be used?

Step by Step Solution

3.44 Rating (147 Votes )

There are 3 Steps involved in it

Step: 1

Wet Sandy Material Excavation 1 Total Loose Material Volume Bank Volume wet dense 15300 m Swell Factor 25 Loose Material Volume Bank Volume 1 Swell Fa... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tax Research

Authors: Barbara H. Karlin

4th Edition

013601531X, 978-0136015314

More Books

Students also viewed these Finance questions

Question

=+2. Why would fans care about something that happened in 1836

Answered: 1 week ago