A contractor is interested in the total cost of a project on which he intends to bid. He knows that his costs will be $600
A contractor is interested in the total cost of a project on which he intends to bid. He knows that his costs will be $600 per day (for labour), plus a fixed cost of $15,000 (for materials, etc.). The contractor forms subjective probability assessments of the number of days,Y, that will be required to complete the project as shown below:
Y
1
2
3
4
5
p(y)
0.1
0.3
0.3
0.2
0.1
- [2]Find the expected number of days needed to complete the project,Y.
- [2]Find the variance of the completion time,Y.
- [3]What is the expected value of the total cost of the project?
- [3]What is the standard deviation of the total cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started