Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A contractor plans to use a wheeled loader to move 5,000 BCY of soil 500 feet using a 50-minute working hour. The soil has a

A contractor plans to use a wheeled loader to move 5,000 BCY of soil 500 feet using a 50-minute working hour. The soil has a swell of 15%. The loader has a bucket capacity of 2.5 cubic yards. The soil has a fill factor of 1.2 and a weight of 2,500 lbs per LCY. The loader has an STL of 50% of 15,000 lbs. The loader will haul in one direction loaded at 2.5 miles per hour and return at 3.5 miles per hour. The total cost of the tractor is $55.00 per hour. It has a fixed time of .35 minutes. Remember that the loader will be moving the dirt in its loose state. 

What is the productivity of the loader in LCY per hour? 


Step by Step Solution

3.47 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to Geotechnical Engineering

Authors: Robert D. Holtz, William D. Kovacs, Thomas C. Sheahan

2nd edition

132496348, 978-0132496346

More Books

Students also viewed these Mechanical Engineering questions

Question

Solve each equation. x 3 - 6x 2 = -8x

Answered: 1 week ago