Question
A contractor sends a final billing report to a city requesting payment on a new fire station. City personnel inspect the building and approve payment
A contractor sends a final billing report to a city requesting payment on a new fire station. City personnel inspect the building and approve payment of the accumulated retainage of $8 million. The total amount billed to the city for the project was $80 million. Which account and amount is debited to record the payment of the retainage to the contractor in a Capital Projects Fund?
Select one:
a. Expenditures - construction cost is debited for $72 million.
b. Expenditures - construction cost is debited for $8 million.
c. Retainage payable should be debited for $72 million.
d. Retainage payable should be debited for $8 million.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started