Question

1 Approved Answer

A cost centre has an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours. In the

A cost centre has an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours.

In the period covered by the budget, actual machine hours worked were 2% more than the budgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389.

What was the total over or under absorption of overheads in the cost centre for the period?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

3rd Edition

0324226063, 978-0324226065

More Books

Students also viewed these General Management questions

Question

What is the purpose of a range check?

Answered: 1 week ago

Question

How did NUMMI give workers some control over the production line?

Answered: 1 week ago