A cost estimate that is -25% to +75% of actual is considered a(n): Question 19 options: a) Definitive estimate. b) Parametric estimate. c) Budget estimate
A cost estimate that is -25% to +75% of actual is considered a(n): Question 19 options: a) Definitive estimate. b) Parametric estimate. c) Budget estimate d) Rough order of magnitude estimate