Question

1 Approved Answer

A crew of drywallers, which includes 3 drywall hangers and 1 finisher, can install 3,000 square feet of drywall (also called sheetrock) per day on

A crew of drywallers, which includes 3 drywall hangers and 1 finisher, can install 3,000 square feet of drywall (also called sheetrock) per day on walls and 2,000 square feet on the ceiling, including one (1) coat over all of the joints; the crews are working standard 8- hour days, 5 days a week. Assuming an extra 6 days is required for the finisher to sand and put a second and third coat over the joints, how many working days will it take to install and finish the drywall on a structure with interior dimensions of 200 long x 75 wide x 12 tall? Do not consider interior walls or partitions, use the measurements provided above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: John R., Jr. Schermerhorn, Barry Wright

3rd Canadian edition

1118789296, 1118789292, 978-1118789292

More Books

Students also viewed these General Management questions